【问题标题】:Visualizing time frame data expressed in ranges of dates可视化以日期范围表示的时间范围数据
【发布时间】:2013-02-05 20:31:39
【问题描述】:

我想将下面给出的五个项目的时间框架数据可视化。目前我正在使用 OpenOffice 绘图应用程序并手动生成如下所示的图表。但我不满意。你能帮我解决以下问题吗?谢谢。

1. How can I produce somewhat similar graphs using R (or excel) with better precision in terms of days? 
2. Is there a way for better visualization of the data? If so, please let me know how to produce that using R or Excel. 

Project     Time
-------    ------ 
A   Feb 15 – March 1
B   March 15 – June 15
C   Feb 1 – March 15
D   April 10 – May 15
E   March 1 – June 30

【问题讨论】:

    标签: r data-visualization


    【解决方案1】:

    ggplot2 提供了一种(相当)直接的方式来构建绘图。

    首先,您需要将数据输入R。你希望你的开始和结束日期是某种Date 格式的R(我用过Date

    library(ggplot2)
    library(scales) # for date formatting with ggplot2
    
    DT <- data.frame(Project = LETTERS[1:5], 
      start = as.Date(ISOdate(2012, c(2,3,2,4,3), c(15,15,1,10) )),
      end = as.Date(ISOdate(2012, c(3,5,3,5,6), c(1,15,15,15,30))))
    # it is useful to have a numeric version of the Project column (
    DT$ProjectN <- as.numeric(DT$Project)
    

    您还需要计算文本的放置位置,我将使用 plyr 包中的 `ddply1

    library(plyr)
    # find the midpoint date  for each project
    DTa <- ddply(DT, .(ProjectN, Project), summarize, mid = mean(c(start,end)))
    

    你想创造

    • 每个项目的矩形,因此您可以使用geom_rect
    • 每个中点的文本标签

    这是一个如何构建情节的示例

    ggplot(DT) + 
       geom_rect(aes(colour = Project,ymin = ProjectN - 0.45, 
                    ymax = ProjectN + 0.45,  xmin = start, xmax = end)), fill = NA) + 
      scale_colour_hue(guide = 'none') +  # this removes the legend
     geom_text(data = DTa, aes(label = Project, y = ProjectN, x = mid,colour = Project), inherit.aes= FALSE) + # now some prettying up to remove text / axis ticks
      theme(panel.background = element_blank(), 
            axis.ticks.y = element_blank(), axis.text.y = element_blank()) + # and add date labels
      scale_x_date(labels = date_format('%b %d'), 
      breaks = sort(unique(c(DT$start,DT$end))))+ # remove axis labels
      labs(y = NULL, x = NULL) 
    

    【讨论】:

      【解决方案2】:

      您还可以检查 plotrix 包中的 gantt.chart 函数。

      library(plotrix)
      ?gantt.chart
      

      这是一个实现

      dmY.format<-"%d/%m/%Y"
      gantt.info<-list(
        labels= c("A","B","C","D","E"),
        starts= as.Date(c("15/02/2012", "15/03/2012", "01/02/2012", "10/04/2012","01/03/2012"),
                        format=dmY.format),
        ends= as.Date(c("01/03/2012", "15/06/2012", "15/03/2012", "15/05/2012","30/06/2012"),
                      format=dmY.format)
        )
      
      vgridpos<-as.Date(c("01/01/2012","01/02/2012","01/03/2012","01/04/2012","01/05/2012","01/06/2012","01/07/2012","01/08/2012"),format=dmY.format)
      vgridlab<-
        c("Jan","Feb","Mar","Apr","May","Jun","Jul","Aug")
      
      gantt.chart(gantt.info, xlim= c(as.Date("01/01/2012",format=dmY.format), as.Date("01/08/2012",format=dmY.format)) , main="Projects duration",taskcolors=FALSE, border.col="black",
                  vgridpos=vgridpos,vgridlab=vgridlab,hgrid=TRUE)
      

      我也试过 ggplot2。但是 mnel 比我快。这是我的代码

      data1 <- as.data.frame(gantt.info)
      data1$order <- 1:nrow(data1)
      
      library(ggplot2)
      
      ggplot(data1, aes(xmin = starts, xmax = ends, ymin = order, ymax = order+0.5)) + geom_rect(color="black",fill=FALSE) + theme_bw()  + geom_text(aes(x= starts + (ends-starts)/2 ,y=order+0.25, label=labels)) +  ylab("Projects") + xlab("Date") 
      

      【讨论】: